SB1285- construction contracts’ public works;
payments This bill requires a contractor to
submit a billing estimate for: 1. The retention release after a substantial completion
of work in a contract; and 2. The final payment after final completion of
work in a contract. Specifies that a billing or estimate for
retention release or final payment is deemed certified within 7 days of the entities
receipt, unless a written statement is issued detailing the reasons for denial.
Requires a governmental entity to pay
retention release or make final payment to a contractor within 14 days of
certification and approval of the billing or estimate. Allows a contractor or subcontractor
for a contract to request payment for any changed or additional work requested
by a government entity that was
completed in the preceding calendar month in monthly payment estimates based on
the costs incurred to perform the work. Requires the person designated in the
contract with the responsibility for certifying and approving monthly payment
estimates to make an interim determination to approve paying monthly costs and
certify the amount determined to be reasonably justified. Requires a government entity to
specify the reasons for not approving all or any portion of an estimate of work
performed in a request for progress payment regarding a contract. Allows a government entity to decline
to certify and approve an estimate or portion of a billing or estimate and allows
a contractor or subcontractor to withhold an application and certification for
payment to a subcontractor or material supplier for: 1. Unsatisfactory job progress; 2. Defective construction work or materials not
remedied; 3. Disputed work or materials; 4. Failure to comply with provisions of the contract; 5. Failure of a contractor or subcontractor to
make timely payments for labor, equipment and materials; 6. Claims filed by third-parties; 7. Damage to the government entity; or 8. The existence of reasonable evidence that the
contract cannot be completed for the unpaid balance of the contract sum. Allows a government entity to: 1. Decline to certify and approve all or a
portion of a billing or estimate for retention release or final payment due to
the contractors failure to complete a material requirement of the contract,
failure to complete a portion of the work or other outlined reasons; or 2. Withhold up to 150% of the direct costs and
expenses that the government entity reasonably expected to incur for protection
for which the contractor is responsible. Allows a contractor to submit a
supplemental billing or estimate for any amounts withhold by a government
entity from retention release or final payment if any reason for a declined
payment has been removed. Prohibits a contractor from submitting
more than one billing or estimate during each billing cycle, unless otherwise
agreed. Specifies that performance by a contractor,
subcontractor, material supplier or design professional in accordance with the
terms of a contract entitles them to payment from the contracting government entity.
Requires a contractor, subcontractor
or design professional to pay the full amount received for work completed in
accordance with the contract within 7 days of receiving any progress payment,
retention release or final payment. Specifies that payment by a
contractor, subcontractor, or design professional is not required unless they provide
a billing or invoice for work performed or materials supplied. Allows a contractor or subcontractor
to be paid as outlined in a contract, unless the contractor provides written
consent to modify any payment or certification timelines. Prohibits a contract for the
procurement of construction to include a provision that limits or precludes a
contractors recovery of damages related to expenses incurred by the contractor
for a delay: 1. For which the government entity is responsible; 2. That is unreasonable under the circumstances;
and 3. Provide any other procedure for the settlement
or provision of liquidated damages. Requires the successful party in any action
or arbitration brought to collect payments or interest in a contract to be
awarded reasonable attorney fees and costs. Allows, rather than requires, a
subcontractor or material supplier to notify ROC and the government entity of
any payment received by a contractor in an amount less than the percentage
approved for the class or item of work performed. Prohibits a contractor or
subcontractor from withholding retention from a subcontractor in an amount greater
than the actual amount of the retention returned by the government entity
pertaining to the subcontractors work. Requires a contractor that chooses to withhold
the application or certification for a subcontractor or material suppliers billing
or estimate to provide written notice within 14 days that outlines the reasons
for withholding. Requires a contractor to send a copy
of any statement regarding refusal to certify or approve the billing or
estimate by a government entity to any affected subcontractor or material supplier
with 7 days. Requires a subcontractor, after receiving
a statement from a subcontractor regarding a refusal to certify or approve billing
or estimate by a government entity, to send a copy of the statement to any
affected subcontractors or material suppliers with 7 days. Requires a contractor, after receiving
notice from a government entity of a refusal to certify or approve billings or
estimates for defective construction work or materials not remedied, to pay any
subcontractor or material supplier whose work was not the basis for withholding
within 21 days of the date the payment would have otherwise been made. Allows ADOT to retain 5% of all
estimates as a guarantee for complete performance of a highway construction
contract. Allows any government entity except
ADOT to retain 5%, rather than 10%, of the amount of each progress payment
estimate for a contract until final completion and acceptance is deemed
approved as a guarantee for complete performance of the contract. Permits a government entity to opt to have
no retention on a contract. Removes the requirement that half of
any amount retained by a government entity, except ADOT, be paid to the
contractor when half the contract is completed. Specifies that any provision affecting
a construction-manager-at-risk, design build or job-order-contracting contract
with the state or political subdivision is void and unenforceable if it
subjects the contract to the laws of another state or requires any litigation
arising from the contract to occur in another state. Removes language requiring a contractor
to be paid any amount withheld by the state or a political subdivision as a guarantee
for complete contract performance within 60 days of final completion. Allows a material supplier to request
notification from a government agency within 5 days of any progress payment
made to the contractor. Allows a contractor or subcontractor
to suspend performance or terminate a contract due a government entity's
failure to timely pay any certified and approved amount. Requires that notice of intention to
suspend or terminate a contract, due to failure to timely pay by a government
entity, be provided: a) seven days
before executing a suspension or termination for a contractor; and b) three days before executing a suspension
or termination for a subcontractor. Specifies that a contractor or
subcontractor is not deemed in breach of a contract for suspension of
performance or termination due to the failure of a government entity to timely
pay. Allows a subcontractor to suspend
performance or terminate a contract if a government entity: a) timely pays
certified and approved amounts, but the contractor fails to pay the
subcontractor; or b) declines to approve and certify portions of
the contractor's billing or estimate for the subcontractor's work, but the reasons
for withholding of approval are not the fault of, or directly related to, the
subcontractor's work. Requires notice of intention to
suspend or terminate a contract by a subcontractor for reasons other than a
failure to pay by the government entity to be provided to the government entity
and the contractor seven days before executing a suspension or termination,
unless a shorter period is required in the contract. Specifies that contractors and subcontractors
that suspend performance for authorized reasons are not required to furnish
further labor, materials or services until the contractor or subcontractor is
paid the amount that was certified and approved, plus any costs incurred for
mobilization resulting from the shut down and start-up of a contract. Requires written notice of a
suspension or termination of a contract to be: a) delivered in person to the
individual or member of the entity for which it was intended; or b) delivered
or sent by means that provide written third-party verification of delivery to
the last known business address of the entity.
Specifies that a provision, covenant
or clause relating to a contract is void and unenforceable if it states that a
party cannot suspend or terminate the contract if another party fails to make
prompt payments pursuant to statute. Exempts agricultural improvement
districts and electric cooperatives from the definitions of contractor and
subcontractor relating to void and unenforceable contract clauses. Specifies that any diversion by the
contractor or subcontractor of payments received or failure to reasonably
account for the application of payments, constitutes grounds for disciplinary
action by the ROC, including suspension or revocation of a license. Requires any licensed contractor or
licensed subcontractor or material supplier that files a complaint with the ROC
relating to payment of contract work to post a surety bond or cash deposit of
$500 or half the amount due, whichever is less, with the ROC to secure the
payment of claims. Requires the ROC to order a
complainant who files any claim determined to be without merit and frivolous to
pay: a) half of the amount of the required
surety bond or cash deposit to the respondent; and b) half of the amount to the ROC for deposit
into the state General Fund. Requires that the surety bond or cash
deposit be: a) returned to the complainant if a claim is not made against the
surety bond or cash deposit; and b) in the name of the licensed contractor,
licensed subcontractor or material supplier that files the complaint. Specifies that the security bond or
cash deposit is conditioned on and must provide for payment on the presentation
of a certified copy of a ROC order and a certification by the complainant of
nonpayment within 30 days of the final ROC order. Requires that the surety bond be
executed by the complainant as principal with an authorized surety corporation
in Arizona. Requires that evidence of the surety
bond be submitted to the ROC in an acceptable form. Requires that the cash deposit be
deposited by the ROC in the Contractors Prompt Pay Complaint Fund and held to
pay claims. Requires the procurement rules for
school districts adopted by the State Board of Education to strictly comply
with prompt payment requirements |