Source: John Downey, TRIAD BUSINESS JOURNAL, 1/16/19
Two recent rulings federal court rulings could delay construction of the Atlantic Coast Pipeline for up to a year and add as much as $1 billion more to costs already estimated at up to $7 billion. That could push completion of the 600-mile project — designed to transport natural gas from shale fields in the North and Midwest from West Virginia, through coastal Virginia and to eastern North Carolina — back to mid-2021. And that is only if the pipeline ultimately wins court challenges. For more of this story, click here.
|